Construction continues at Arena de Sao Paulo, where FIFA general secretary Jerome Valcke visited in January. Two workers died there late last year after the roof collapsed following a crane accident.
Construction continues at Arena de Sao Paulo, where FIFA general secretary Jerome Valcke visited in January. Two workers died there late last year after the roof collapsed following a crane accident.
Friedemann Vogel/FIFA/Getty Images

SAO PAULO (AP) - Brazilian constructors say they have installed the giant roofing structure that collapsed after a crane failure at the stadium hosting the World Cup's opening match in three months.

The accident late last year killed two workers and caused significant damage to the Itaquerao stadium, prompting a delay that should keep the venue from being handed over to FIFA until about a month before the opener between Brazil and Croatia on June 12.

MORE: Arena Amazonia opens in Manaus

Constructor Odebrecht said Monday it took nearly six hours to install the 420-ton, 77-meter-long (250-feet-long) metal structure that runs across one of the stadium's goals.

Odebrecht says the Itaquerao is 98 percent completed and it should be ready on April 15, but FIFA Secretary General Jerome Valcke said recently he expects the venue finalized in mid-May.

Copyright 2014 Associated Press. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.

SI Apps
We've Got Apps Too
Get expert analysis, unrivaled access, and the award-winning storytelling only SI can provide - from Peter King, Tom Verducci, Lee Jenkins, Seth Davis, and more - delivered straight to you, along with up-to-the-minute news and live scores.